Okmetic Oyj

An airtight production facility with energy panels

  • Okmetic Oyj's production facility in Vantaa was finalised in April 2013. It is a great example of Ruukki's energy-efficient solutions. The aims of the developer were energy-efficiency and airtightness in particular.
  • The production process taking place in the facility requires an airtight environment. The airpressure in the building is positive which helps keep out external particles (e.g. dust, harmful agents). Ruukki's airtight energy panel was used in order to secure airtightness in the building.

Ruukki's delivery: 2013
  • Energy panel SPA230E 1,200 m2
  • Load bearing sheets approx. 700 m2
Partners
  • Developer: Okmetic Oyj
  • Contractor: Rakennus Auridos Oy
  • Architectural design: HMT – Arkkitehdit Oy
Piitie, Vantaa, Finland