Ostroleka Biomass Boiler House

Demanding structures and schedule

  • Large and complex structures for a 55 m tall boiler house. In total, 
    Ruukki manufactured 1,300 tones of steel structures.
  • Because of the building height, safety measures had to be taken 
    into special consideration already at the planning stage. All working 
    platforms had to be temporarily secured with railings and all 
    openings covered with thick wooden plates. Around 1 km of railings 
    was used in total.
  • Time schedules for manufacturing and installation were 
    exceptionally tight.
  • Metso valued our advanced Health-Safety-Environment 
    management: regular meetings concerning safety issues and 
    detailed work planning and coordination significantly contributed to 
    work safety.

„Ruukki“ produktai 2009-2010
  • delivery and installation of steel structures for a boiler building, 
    main staircase and roof
Partneriai
  • Investor: Stora Enso
  • Customer: Metso